Project Supply: How an Order Runs from Enquiry to Handover

Request a Quotation

TheEPC and project supply page covers what a project's technical and documentation requirements look like. This page covers project material supply mechanics: what happens at each stage of an order, what information is needed when, and where orders go wrong. Most of the failures are not manufacturing failures. They occur at enquiry, at order clarification and at document handover, which means they are preventable at no cost if they are caught in the right week.

The Stages

Stage

What happens

What it needs from the buyer

1. Enquiry

Take-off reviewed, specification read, gaps identified

Line list, governing specification, service conditions, delivery point, date

2. Clarification

Ambiguities raised before pricing rather than after order

A technical contact who can answer, not only a commercial one

3. Quotation

Priced against the governing specification, with lead time confirmed per item

Confirmation of currency, Incoterm and certification level

4. Order

Items confirmed, testing and inspection scope fixed, documentation requirements agreed

Nominated inspection agency where a 3.2 applies

5. Manufacture or allocation

Mill route or allocation, with hold points observed

Availability for inspection at agreed hold points

6. Inspection and testing

Standard testing plus any supplementary scope

Attendance or waiver, in writing

7. Documentation

Certification package assembled against the order and the specification

Confirmation of who the package has to satisfy

8. Packing and marking

Preservation for the destination and storage duration

Where the material will sit, and for how long

9. Despatch and delivery

Routing, documents, delivery point

Site access and receiving constraints

10. Handover

Material and documents accepted at the gate

Document control contact

Project Supply FAQ

Where do project material orders usually fail?

Before manufacture. At enquiry from an incomplete take-off, at clarification from a missing technical contact, and at order from certification decided too late.

Why is a technical contact needed as well as a commercial one?

Because commercial contacts cannot approve a deviation or confirm a service condition, so a technical question routed only through procurement waits.

How should a part delivery be split?

By construction sequence rather than material availability. A complete set for one system is worth more than a partial set for three.

Which items are most often left off a project list?

Bolting, gaskets, small bore fittings and thread protectors, because they are bought as commodities even where the service gives them their own requirements.

Whose documentation requirements apply?

Those of the party that will inspect on arrival. Material approved by a head office and received by a site needs the package the receiving party checks.

What is the most useful flexibility a buyer can offer?

Saying in the enquiry whether a split delivery is acceptable, because it often turns a missed date into a met one.